Road Works at Amotherby Crossroads

Please be aware that road works will take place at Amotherby crossroads w/c Mon 3rd, including kerbing below the banking and railings, and resurfacing of all four arms of the crossroads.

The Amotherby Parish Council has received the following information from Highways:- Work is planned to occur over 3 nights–Mon 3rd to Wed 5th inclusive, from 6pm to midnight (the 6am on the notices is to allow for slight delays). If kerbing work is not completed it may be necessary to also close the C20 into the village on Thursday evening to complete this. The main B1257 will not be completely shut; there will be traffic lights in operation. The C20 down into the village will be completely closed for the 3 nights to allow for kerbing to be done–no access will be possible after 6pm (8pm on Monday to allow traffic for the school disco through).

Monday – kerbing on the C20 and preparatory work on the westbound B1257 (traffic towards Hovingham) and up Amotherby Lane, but not as far as the Parish Hall entrance. It will be possible to access the Parish Hall from the top of Amotherby Lane (Castle Howard road).

Tuesday – kerbing on the C20 and preparatory work on the eastbound B1257 (traffic towards Malton) and down into the village. It will be possible to access the Parish Hall from the B1257.

Wednesday – kerbing on the C20 and complete the surfacing on all four parts of the crossroads, so access to the Parish Hall is dubious from the B1257, but possible from the Castle Howard road. Highways have promised to notify us of any change to this schedule due to hold ups caused by weather.